Heavy Lifting
De Groote - Lifting project
For this project with ArcelorMittal, a gas pipe with a large diameter needed to be relocated. A 34-hour shutdown was planned during which the setup, execution, and dismantling of the manipulation equipment had to take place. De Groote nv contacted Caden, a specialist in heavy lift and transportation.
Caden developed a comprehensive step-by-step plan with a time schedule for each phase to demonstrate feasibility. Thanks to thorough preparation and precise execution, the partnership between ArcelorMittal and De Groote nv has continued for several projects since then.